Welcome to the Gunter ISD Bond Construction Website
On May 7, 2022, Gunter ISD voters approved a bond election for $78.8 million to address growth and student opportunities. Follow along with the progress being made on the bond projects by checking the updates on this website.
LATEST UPDATES
High School / Middle School
Building D - Gymnasium Pad Preparation
Building C – Pad Preparation
Building C – Moisture Conditioning
Building A – Mechanical Rough-in and Roofing
Elementary School
All Underground Storm and Water Utilities are in place and completed.
Interior Building Plumbing and Electrical underground are currently ongoing.
Building Foundations Systems and Building Slab Phases are currently ongoing.
Structural Bar Joist and Decking for the Building Phases are ongoing as sequenced delivery.
Insulated Concrete Forms (ICF) has been delivered and currently being installed for the Storm Shelter Phase.
Preston Crossing Drive extension currently underway with temporary Construction routed to Karsten Ridge Pass.