Welcome to the Gunter ISD Bond Construction Website

On May 7, 2022, Gunter ISD voters approved a bond election for $78.8 million to address growth and student opportunities. Follow along with the progress being made on the bond projects by checking the updates on this website.

LATEST UPDATES

High School / Middle School

  • Building D - Gymnasium Pad Preparation

  • Building C – Pad Preparation

  • Building C – Moisture Conditioning

  • Building A – Mechanical Rough-in and Roofing

Elementary School

  • All Underground Storm and Water Utilities are in place and completed.

  • Interior Building Plumbing and Electrical underground are currently ongoing.  

  • Building Foundations Systems and Building Slab Phases are currently ongoing.  

  • Structural Bar Joist and Decking for the Building Phases are ongoing as sequenced delivery.

  • Insulated Concrete Forms (ICF) has been delivered and currently being installed for the Storm Shelter Phase.  

  • Preston Crossing Drive extension currently underway with temporary Construction routed to Karsten Ridge Pass.